Britt Construction v. Magazzine Clean, LLC

No. 051004Supreme Court of Virginia

051004 Britt Construction v. Magazzine Clean, LLC 01/13/2006 Code § 43-4 requires a general contractor, as a condition of perfecting a mechanic's lien, to contemporaneously file with the memorandum of lien a "…

The clerk's words are shown exactly as filed.
01
The caption

The parties exactly as the court lists them—not a claim about the merits.

02
The activity

Orders, motions, and filings in the clerk's own words and sequence.

03
The source

The official docket and available court documents attached to every update.

Current update

051004 Britt Construction v. Magazzine Clean, LLC 01/13/2006 Code § 43-4 requires a general contractor, as a condition of perfect…

At a glance
Court
Supreme Court of Virginia
First added here
October 4, 2026
Last entry
January 13, 2006
Policy at issue

No bill or executive-order citation is attached to this file.

Official docket

Case timeline

The clerk's wording is shown verbatim and linked to the court's own document page where available.

Docket entry

051004 Britt Construction v. Magazzine Clean, LLC 01/13/2006 Code § 43-4 requires a general contractor, as a condition of perfecting a mechanic's lien, to contemporaneously file with the memorandum of lien a "certification" that a copy of the memorandum has been mailed to the property owner. Therefore, the circuit court correctly held that 12 mechanic's liens filed by a general contractor were invalid, and properly released a construction project owner's property therefrom, where the general contractor failed to contemporaneously file certifications of mailing along with the memoranda of liens. The judgment of the circuit court is affirmed.

Open court document ↗

Rulings in this case over time

Courts at different levels and stages can reach different results in the same case. Each entry is the court's own record; read it before drawing a conclusion.

1 entry, oldest first.

  1. · Supreme Court of Virginia

    Affirmed

    The court's record, as written

    051004 Britt Construction v. Magazzine Clean, LLC 01/13/2006 Code § 43-4 requires a general contractor, as a condition of perfecting a mechanic's lien, to contemporaneously file with the memorandum of lien a "certification" that a copy of the memorandum has been mailed to the property owner. Therefore, the circuit court correctly held that 12 mechanic's liens filed by a general contractor were invalid, and properly released a construction project owner's property therefrom, where the general contractor failed to contemporaneously file certifications of mailing along with the memoranda of liens. The judgment of the circuit court is affirmed.

    Outcome words in this text: affirmed.

Method: an entry is marked with an outcome only when its own text contains the outcome word, and the word is shown beside it. Orders, opinions and judgments whose text does not say are marked Other. Party filings, notices and routine procedural orders (appearances, extra pages, time extensions, scheduling) are not listed. No link between this case and any other case is recorded in our data, so only this case's own record is shown. Open the court's docket