The parties exactly as the court lists them—not a claim about the merits.
Piedmont Environmental Council v. VEPCO
090249 Piedmont Environmental Council v. VEPCO 11/05/2009 In consolidated appeals of right from an order of the State Corporation Commission granting, subject to certain conditions, the applications of two ele…
The clerk's words are shown exactly as filed.Orders, motions, and filings in the clerk's own words and sequence.
The official docket and available court documents attached to every update.
090249 Piedmont Environmental Council v. VEPCO 11/05/2009 In consolidated appeals of right from an order of the State Corporation…
- Court
- Supreme Court of Virginia
- First added here
- October 4, 2026
- Last entry
- November 5, 2009
No bill or executive-order citation is attached to this file.
Case timeline
The clerk's wording is shown verbatim and linked to the court's own document page where available.
090249 Piedmont Environmental Council v. VEPCO 11/05/2009 In consolidated appeals of right from an order of the State Corporation Commission granting, subject to certain conditions, the applications of two electric utilities for the construction and operation of Virginia segments of a proposed interstate electric transmission line to be operated by a regional transmission entity that is subject to federal regulation, the record manifestly demonstrates that the Commission conducted its review of the applications in accord with the requirements of Code §§ 56-46.1 and 56-265.2, and that the Commission's decision to grant the applications is supported by the evidence. The Commission's order, as…
Open court document ↗Rulings in this case over time
Courts at different levels and stages can reach different results in the same case. Each entry is the court's own record; read it before drawing a conclusion.
1 entry, oldest first.
· Supreme Court of Virginia
Granted
The court's record, as written
090249 Piedmont Environmental Council v. VEPCO 11/05/2009 In consolidated appeals of right from an order of the State Corporation Commission granting, subject to certain conditions, the applications of two electric utilities for the construction and operation of Virginia segments of a proposed interstate electric transmission line to be operated by a regional transmission entity that is subject to federal regulation, the record manifestly demonstrates that the Commission conducted its review of the applications in accord with the requirements of Code §§ 56-46.1 and 56-265.2, and that the Commission's decision to grant the applications is supported by the evidence. The Commission's order, as…
Outcome words in this text: granting.
Method: an entry is marked with an outcome only when its own text contains the outcome word, and the word is shown beside it. Orders, opinions and judgments whose text does not say are marked Other. Party filings, notices and routine procedural orders (appearances, extra pages, time extensions, scheduling) are not listed. No link between this case and any other case is recorded in our data, so only this case's own record is shown. Open the court's docket